Client Electricity North West (ENW)

Outline Project

  • Refurbishment of 3No 132kV circuits routed from Carrington to Barton, Greater Manchester.
  • Largest ENW scheme during 5 year Ofgem review period
  • EDES rationalised preliminary design produced by others resulting in £1.4m saving on project budget.

EDES Involvement

  • Design elements of cable / overhead line replacement.
  • Project management of cable installation from initial cable calculations to jointing cables and commissioning circuits.